REPORT OF THE COMMITTEE |
Tuesday, December 4, 2001 |
The Standing Senate Committee on National Finance
has the honour to table its
TENTH REPORT
Your Committee, to which were referred the Supplementary Estimates "A", 2001-2002, has, in obedience to the Order of Reference of 6 November 2001, examined the said estimates and herewith tables its report.
Respectfully submitted,
Lowell Murray
Chairman
Report on Supplementary Estimates (A) 2001-2002
Your
Committee held a meeting on Wednesday, 21 November 2001 to review these
supplementary estimates. At this
meeting, officials of the Treasury Board Secretariat appeared as witnesses and
provided three explanatory tables, which form part of this report. Together the
tables summarize the major changes in the federal government’s financing
requirements in fiscal 2001-2002. Supplementary
Estimates “A” is the first of a set of supplementary estimates that will be
issued in this fiscal year that ends on March 31, 2002.
OVERVIEW
Table 1, entitled
“Summary of Expenditure Framework and Estimates for 2001-2002,” provides a
quick summary of the original estimates.
Table 2, entitled “Estimates to Date 2001-2002” outlines the
changes as proposed by these supplementary estimates.
Total planned spending will rise from $165.2 billion to $172.4 billion.
The bulk of these expenditures, $114.9 billion or 66.6%, are statutory
expenditures that do not require a vote.
The $7.2 billion change in
the total estimates proposed in the supplementary estimates represents a 4.4%
increase in the original planned government expenditures for fiscal 2001-2002.
Table
1
SUMMARY
OF EXPENDITURE FRAMEWORK AND
ESTIMATES
FOR 2001-2002
Expenditure
Framework: |
|
Budgetary
Main Estimates |
$163.4
billion |
Budgetary
Estimates to Date |
$163.4
billion |
Projected
Budgetary Estimates |
$167.1
billion |
Table 2
ESTIMATES TO
DATE FOR 2001-2002
|
TO
BE VOTED |
STATUTORY |
TOTAL |
|
(In
thousands of dollars) |
||
Main Estimates |
|
|
|
*Budgetary |
$52,334,584 |
$111,021,549 |
$163,356,133 |
Non-Budgetary |
76,403 |
1,803,601 |
1,880,004 |
|
|
|
|
|
$52,410,987 |
$112,825,150 |
$165,236,137 |
Supplementary
Estimates (A) |
|
|
|
Budgetary |
$4,823,998 |
1,946,387 |
$6,770,385 |
Non-Budgetary |
6,000 |
176,530 |
182,530 |
|
|
|
|
|
$4,829,998 |
2,122,917 |
$6,952,915 |
**Unexpended
Funds |
|
|
|
Budgetary |
$204,112 |
- |
$204,112 |
Non-budgetary |
- |
- |
- |
|
$204,112 |
- |
$204,112 |
***Total
Estimates to Date |
|
|
|
Budgetary |
$57,362,694 |
$112,967,936 |
$170,330,630 |
Non-Budgetary |
82,403 |
1,980,131 |
2,062,534 |
|
|
|
|
|
$57,445,097 |
$114,948,067 |
$172,393,164 |
*
Estimates
will always differ from Projected Budgetary Expenditures due to adjustments not
reflected in Estimates for such items as anticipated lapses, budgetary
reductions and those expenditures already recognized in prior years.
** This amount represents unexpended funds that
were appropriated in 2000-2001 for CCRA and Parks Canada and which will be spent
in 2001-2002.
*** Totals may differ from those shown in the Blue Book due
to rounding.
The third table
entitled “Supply to Date for 2001-2002” summarizes the appropriations that
have been approved to date. Appropriation Act No. 1 approved $16.3 billion to date, while Appropriation
Act No. 2 approved another $36.1 billion.
Total approved appropriations stand at $52.4 billion.
The current Supplementary Estimates (A) would add a further $4.8 billion,
to increase the total appropriations to $57.4 billion.
In addition, the table reveals that a total of $204.1 million in approved
spending is being carried forward from 2000-2001.
Table
3
SUPPLY
TO DATE FOR 2001-2002
Unexpended
funds appropriated in 2000-2001,
which
will be spent in 2001-2002
$204,111,562.00
Two Appropriation Acts have been approved in respect of the Estimates for 2001-2002
Supply
Approved to Date: |
|
Appropriation Act No. 1, 2001-2002 |
|
Granted
Interim Supply for the 2001-2002 Main Estimates equal to an initial
allocation of 3/12ths for all votes and 43 votes received additional
proportions |
|
$16,343,875,327.99 |
|
|
|
|
|
Appropriation
Act No. 2,2001-2002 |
|
Granted
Full supply for the 2001-2002 Main Estimates |
$36,067,113,419.01 |
|
|
Total
Approved to Date |
$52,410,988,747.00 |
|
|
Supply Awaiting Approval: |
|
For
the whole of Supplementary Estimates (A) 2001-2002 |
|
$4,756,446,373.00 |
|
|
|
Total
for 2001-2002 |
$57,371,546,682.00 |
Supplementary
Estimates “A” 2001-2002 forecast the spending requirements for departments or agencies of the federal government, and as usual,
Senators showed interest in both the general spending plans and specific items
in these new estimates.
Mr. Rick Neville and Mr. David
Bickerton, officials from the Treasury Board of Canada, outlined some of the
significant changes in the Estimates and responded to questions from the Members
of the Committee. They noted that
items included in these Supplementary Estimates serve two purposes.
They seek Parliament’s authority to spend monies, which were provided
for in the fiscal plan set out in the October 2000 Economic Statement and Budget
Update and which were adjusted to include the impact of the policy initiatives
announced in the May 2001 Economic Update.
These Estimates were not included in the 2001-2002 Main Estimates.
The second purpose
of these estimates is to provide Parliament with information about changes in
projections of statutory spending it has already approved in legislation.
These changes amounting to $2.1 billion include a $1.25 billion grant to
the Canadian Foundation for Innovation and an increase of $ 616.0 million in
fiscal equalization payments to provinces.
The
larger, government-wide items include:
- $425.9
million for 69 departments and agencies under the carry-forward provision to
meet operational requirements originally provided for in 2000-2001.
This provision is designed to improve cash management by allowing
managers to carry forward, from one fiscal year to the next, an amount of up
to 5% of their operating budget of the previous fiscal year;
- $382.3
million for compensation for collective bargaining;
- $216.5
million to 27 departments and agencies for incremental funding to address
core operational and capita requirements;
- $164.6
million to 10 departments and agencies for incremental information
management and technology infrastructure requirements;
- $114.4
million for the Canadian Firearms Program; and
- $100.0
million for the Sustainable Development Technology Fund.
Large
requests by single organizations include:
- $550.0
million to Agriculture and Agri-Food Canada under the Farm Income Protection Act for contributions to farmers to
provide immediate assistance to help them deal with hardships experienced
last year;
- $225.3
million to the Canada Customs and Revenue Agency to address operational
workload pressures and pursue revenue generation initiatives;
- $221.9
million to Transport Canada to provide assistance to air carriers ($160.0
million) for losses incurred due to the temporary closure of Canadian air
space and additional payments to VIA Rail in support of an expanded capital
investment program ($61.9 million);
- $152
to National Defence for additional costs associated with training and with
compensation;
- $114.8
million to Fisheries and Oceans Canada for the Fisheries Access program; and
- $109.7
million to the Canadian Institutes of Health Research for program
enhancements.
In its review of the
estimates, the Committee expressed an interest in a number of spending items.
For instance, it noted that the Canada Custom and Revenue Agency is
seeking an additional $287.9 million increase over its original appropriation of
$2.4 billion. This new request
represents a 12.2% increase in the Agency’s original budget.
Most of the requested funding is to address operational workload
pressures and to pursue revenue generation initiatives.
Mr. Neville assured the Committee that these “operational workload
pressures” are not related to the events of 11 September.
Government expenditure items related to measures being taken as result of
the events of 11 September are more likely to appear in subsequent estimates.
The budget of the
Department of Finance is usually quite large relative to other departments, and
its supplementary funding requirements are also usually significant.
These supplementary estimates of the Department are no different.
Two pairs of estimates attracted the Committee’s interest. Under Vote 2a, the Department requests appropriations for the
forgiveness of certain debts and obligations amounting to $17.9 million owed by
the Government of Jamaica. Further on in the estimates of the Canada
International Development Agency (CIDA), there is a request for an appropriation
under Vote 25 to provide a $20.0 million grant to Jamaica.
A second pair of transactions involves a reduction of $40.5 million in
Canada’s payments to the International Monetary Fund’s Poverty Reduction and
Growth Facility and a statutory advance of $172.0 million to the same program.
While such transactions might give the impression that one part of the
government is not aware of activities in the other, Mr. Neville assured the
Committee that the Government is fully aware of these apparently offsetting
transactions. He explained that as
these items involve different types of transactions (i.e. loans versus grant or
payments versus loans) it is necessary that each transaction be itemized.
The Committee noted that
additional funding in the order of $158.6 million (an increase of 51.5%) is
required by the Department of Justice to cover its operating expenditures.
The largest proportion of the increase ($90.5 million) is dedicated to
the Canadian Firearms Program. A
smaller but significant amount of $26.6 million is allocated to cover the
additional cost for unique legal cases. The
costs surrounding the Firearms Control Program continue to be of concern to
Senators. Since inception, the
overall cost of implementing the program, including current planned spending,
will reach $689.67 million. This amount is well in excess of the original forecasted
implementation costs provided at the time that the program was being considered
in Parliament. Mr. Neville suggests
that the original cost estimates were valid, but that numerous changes in the
program, as it was being implemented, are at the root of the cost increases.
Under
Vote 10a, the Department of Agriculture and Agri-Food is requesting
appropriations of $550.0 million to cover contributions for agricultural risk
management-payments in connection with the Farm
Income Protection Act. The
Treasury Board officials explained that this amount was over and above the
amounts set aside for the usual programs under this Act.
The amount consists of a one-time injection of funds to provide immediate
assistance to help farmers with hardships experienced last year.
According to Mr. Neville, the provinces, usually in a
60/40-federal/provincial ratio, matched these contributions.
Senators
are becoming concerned about the supplementary requests of the new agencies
recently created by the government. These
agencies, which include the Canada Custom and Revenue Agency, Parks Canada, and
the Canadian Food Inspection Agency (CFIA) were created in the belief that
removing them from the public service would result in operational savings.
This does not appear to be the case.
For instance, CFIA is seeking an additional $85.8 million under Vote
25a, an increase of 33% over its original estimate for this fiscal period.
The Agency represents a consolidation of all federal food inspection and
quarantine services into a single food inspection agency.
It began operations in April 1997 and reports to Parliament through the
Minister of Agriculture and Agri-Food. The
Agency enhances food safety systems by integrating the delivery of inspection
and quarantine services previously provided by Agriculture and Agri-Food Canada,
Health Canada, Industry Canada and the Department of Fisheries and Oceans
Canada. It provides all inspection
services related to food safety, economic fraud, trade-related requirements, and
animal and plant health programs. The
Committee reminded the officials that the Agency was created to reduce costs and
yet it has returned to obtain relatively large additional appropriations.
The impression is that removing the agency from the public service has
not provided the anticipated economies. Mr.
Neville explained that when these Agencies were set up, careful analysis by
third parties was conducted to establish their A-base funding levels.
He reminded the Committee, that these agencies were also created to
address a host of other concerns besides cost savings.
As these other objectives of the Agencies are addressed, their funding
requirements may increase. Mr. Neville feels that the current request by the agencies
for additional appropriations has been substantiated.
The supplementary estimates
for the Department of Transport lists new appropriations totalling $315.7
million. This represents an
increase of 33.8% over the March appropriations of $934.8 million.
In the Explanation of Requirements section, the Department seeks $1.2
million under Vote 1a – operations and $55.8 under Vote 5a – capital
expenses, for Public security and anti-terrorism initiatives.
Under the heading of grants the Department is asking for $152.0 million
to provide grants to Canadian airlines and specialty air operators, as payments
of financial assistance in respect to losses incurred due to the temporary
closure of Canadian air space following September 11, 2001. Mr. Neville explained that this money was available only to
Canadian carriers and only for itemized expenses that could be clearly related
to the closing of Canadian air space.
Finally, the Committee had
lengthy discussions with the Officials about the decision to advance $100
million to a private corporation to establish the Sustainable Development
Technology Fund. Mr. Neville
recounted the sequence of events and transactions that led to the creation of
the Fund. Briefly, the intention of
the government to create a sustainable development technology fund was announced
in the budget speech in February 2000. Legislation
was initially introduced in the House in October 2000.
With the call of the election, Bill C-46 died on the Order
Paper and was tabled again in February 2001, as Bill C-4.
Royal Assent to Bill C-4 was given on June 14, 2001.
The Act created the Canada Foundation for Sustainable Development
Technology. Between the call of the
election and the granting of Royal Assent to Bill C-4, Treasury Board entered
into a funding agreement with a company, created under the Canada
Corporations Act, on the terms and conditions for the use of a $100 million
grant. As these transaction
transpired too late for inclusion in earlier estimates, they were listed in the
2001-2002 Supplementary Estimates. The
funding was possible through access to Treasury Board Contingencies Vote 5.
The officials of the Treasury Board claimed that these transactions were
acceptable because they were entirely legal.
They reminded the Committee that even the Auditor General agreed that
they were legal. However, the
Auditor General also had reservations about the appropriateness of the
procedures employed to create this Fund.
In
its Eighth Report-The Interim Report on Estimates 2001-2002, the Committee
commented on this series of events when it stated that:
“Senators wondered if this was an appropriate way to create such agencies and crown corporations. They questioned whether the government should have passed the bill before it advanced the funding. The members of the Committee condemn this process, which creates and funds a $100 million agency without prior Parliamentary approval.”
Although
the Committee recognises that these transactions are legal, it continues to
question whether it is advisable to use monies from the Treasury Board
Contingencies Vote to fund new initiatives before the matter has been considered
by Parliament. In spite of repeated
claims that the series of actions were legal, Senators remained unsatisfied with
the overall explanation provided by the officials.
Nor are they alone in this assessment.
On November 22, 2001, the Speaker of the House of Commons ruled that
while he did not find these actions of the government to be illegal, he
nonetheless concluded that:
“…no
authority has ever been sought from parliament for grants totalling $50 million
made to the corporation in April of this year and does not consider that the
notes in the supplementary estimates (A) concerning the disbursement of these
earlier monies are sufficient to be considered as a request for approval of
those grants. In other words, the approval that is being sought in
supplementary estimates (A) cannot be deemed to include tacit approval for the
earlier $50 million grant.”
The Speaker added that the
government could clear up the matter when he stated:
“However, as there remains
ample time for the government to take corrective action by making the
appropriate request of parliament through the supplementary estimates process,
the Chair need not comment further at this time. The supplementary estimates (A)
for 2001-2002 can therefore proceed.
In
light of this ruling the Committee awaits the Government’s corrective action.
The
Committee believes that Parliamentarians are not solely interested in the
legality of actions, but are equally concerned about the accountability of
government to Parliament. A
“done deal” presents Parliamentarians with very little opportunity to
provide thoughtful reflection on the advisability of the actions being
considered. In a broader context,
the Committee continues to have serious reservations about the way in which the
Treasury Board Contingencies Vote 5 is used by the government to fund various
initiatives. Consequently, the
Committee shall examine this practice in greater detail at a later date.